So what remains to be done at Apple Tree Lane? There's a lot! In general, here's the list:
- While the bedrooms are painted with 2 coats, the remaining interior walls and trim need one more coat of paint. That's a lot of painting.
- The lighting needs to be completed including under cabinets, exterior lights and lamposts (if we opt for one).
- The tile work needs at least a week to be completeted. We're still waiting for the accent tiles for the master bath.
- The hardwood flooring, upstairs and downstairs needs to be installed, and then baseboards added.
- The bedrooms need carpeting.
- The island needs to be re-located back to the kitchen.
- Granite countertops need to be finished and installed.
- All the faucets, plumbing fixtures, thermostats etc. need to be installed.
- Appliances need to be installed.
- There's no gas in the propane tank.
- Landscaping...Lots of landscaping.
- We need a drive-way and a mailbox.
- LANDSCAPING
Truly, there are 100's of little details not listed, but one can see that there's lots to do.